Case study · Henley-on-Thames

Old Brewery House, Henley-on-Thames

The conservation and renewal of our own Grade II listed office - using evidence, restraint and contemporary design to give an important 18th-century building its next working life.
Project
Old Brewery House, 86 New Street
Location
Henley-on-Thames, Oxfordshire
Client / Occupier
Cohanim Architecture / Group Property Company
Service
Architecture, Heritage, Planning, Development & Technical Coordination
Key work
Acquisition Strategy, Listed Building Consent, Heritage Research, Repair, Office Refurbishment, Façade Conservation, Building Services & Landscape
Heritage status
Grade II* Listed / Henley Main Conservation Area
Use
Class E Office
Area
Approximately 203 sqm existing office accommodation
Date
2026–ongoing

Old Brewery House is different from most of our projects because we are both architect and occupier. The building became Cohanim Architecture's Henley office in June 2026 and is being progressively repaired, understood and adapted as a long-term home for the practice. It is a Grade II* listed building dating broadly from the second quarter of the 18th century and historically formed part of the Brakspear brewery complex. Originally a high-status residence associated with the brewing family, it later developed an administrative relationship with the brewery and has been in office use for several decades. Our objective is not to return the building artificially to one moment in its history. Instead, we are using its planning record, surviving fabric and physical evidence to determine what is genuinely historic, what has been altered repeatedly and where contemporary intervention can improve the building without eroding the qualities which justify its exceptional listing.

The brief

Becoming custodians rather than simply occupiers The starting brief was to create a high-quality working environment for the practice. The building immediately made that a much more interesting exercise. Old Brewery House contains exceptional Georgian fabric, but also a substantial amount of later work. It underwent alterations in the 1970s, conversion to office use around 1980 and another comprehensive refurbishment in 2003–04. Rather than treating every existing component as though it were 18th century, we began by reconstructing the building's history from archived planning consents, drawings, specifications, photographs and the fabric itself. That research now informs every intervention. The project has consequently become a practical demonstration of our approach to conservation: retain what matters, repair before replacing, identify later interventions accurately, and use contemporary work to improve rather than imitate the historic building.

The challenge

Distinguishing genuine history from later alteration, while staying open every day Old Brewery House contains exceptional Georgian fabric, but a significant amount of what first appears historic dates only from a comprehensive 2003–04 refurbishment. Without accurate archival evidence, listed-building work risks treating later interventions - a lowered basement floor, a renewed rear roof, a partially blocked historic opening, a redecorated interior - as though they carried the same significance as genuinely 18th-century fabric. The practice also had to continue functioning as a working office throughout, so the building could not simply be vacated and returned to. The result is a conservation programme paced by evidence rather than assumption, and delivered while the office remains in daily use.

The building

A Grade II* house within the former Brakspear brewery

Old Brewery House stands on New Street within the Henley Main Conservation Area. Its principal New Street elevation is of particularly high architectural significance: a five-bay Georgian composition with a formal entrance framed by fluted Doric pilasters. To the east, the building has an unusual relationship with the River Thames, including a fine Palladian window and upper-floor river views. The rear faces what is now the Hotel du Vin courtyard but was historically part of the working brewery complex. That distinction between elevations has become important to the design strategy. The principal public elevations are approached with particular restraint, while the much-altered rear and secondary areas provide greater opportunity for carefully evidenced intervention.

Stage one - setting out the lettering
Stage two - applying and burnishing the gold leaf
The finished sign, in gold
The work

Research before design

One of the most important pieces of architectural work has involved no construction at all. We recovered and analysed previous permissions and drawings dating from the 1970s, 1980s, 1990s and particularly the major 2003–04 refurbishment. Those records have established that a surprising amount of fabric which initially appeared historic is in fact considerably later, including: the basement floor having already been lowered substantially in 2003–04; the rear extension roof renewed or altered during the same period; a historic rear opening partially blocked using modern stud construction; significant elements of the internal decorative scheme renewed; roofing details altered previously; and the building having already undergone major office refits. This evidence allows proposals to be directed towards later fabric while retaining genuinely significant material.

Picture or drawing
Fills the card. Photograph: class hc-card-img. Drawing: hc-card-drw. Render: hc-card-ren.
Jun 2026
Removing modern interventions from sensitive rooms

One of the first formal applications concerned the replacement of modern kitchenette and WC fixtures. The Heritage Officer accepted the evidence that these elements were 21st-century additions and that their removal would not affect historic fabric. Listed Building Consent P26/S1216/LB was granted on 16 June 2026. Although modest in physical scale, the consent established the working relationship which has governed the wider project: evidence first, intervention second.

Picture or drawing
Concept image, context photograph or planning drawing.
Aug 2026
Reversing inappropriate previous repair

The external masonry required a different approach. Parts of the building had been repaired using cementitious materials unsuited to the historic masonry. A conservation package was therefore developed comprising removal of inappropriate cementitious mortar, lime repointing, repair of rainwater goods, replacement of locally spalled masonry, and controlled cleaning of the façade. Listed Building Consent P26/S2366/LB was granted on 11 August 2026, with the Heritage Officer describing the proposed works as an enhancement to the listed building.

Render
BIM axonometric or coordination view. Class hc-card-ren - never inverted.
2026 (pre-application)
Making existing space useful before adding new space

The basement currently provides approximately 48 sqm but suffers from highly restricted headroom, varying from around 1.77m to 2.05m. Research established that this is not an untouched Georgian basement. The floor was already lowered by approximately 400mm under the 2003 consent, with its construction subsequently engineered and approved through a further Listed Building Consent in 2004. The current pre-application strategy therefore explores recovering additional headroom by first removing modern suspended ceiling construction and then, only where necessary, lowering the modern floor slab by up to a further 300mm. The historic brick piers, arches and principal structural fabric remain untouched. The purpose is not simply to create more space. It is to relocate WCs, services and ancillary functions into an already altered lower-significance part of the building so that more sensitive upper floors can remain comparatively undivided.

Drawing
Technical section, junction detail or schedule extract. Class hc-card-drw.
2026 (pre-application)
Removing later fabric to recover an earlier elevation

The rear elevation contains one of the most interesting opportunities. Historic drawings demonstrate that the awkward pitched roof over the modern rear extension and the truncation of a former first-floor opening are both consequences of relatively recent work. A new pre-application proposal therefore explores removing the later pitched roof, replacing it with a lower flat roof and discreet terrace, and reinstating the original proportions of the historic opening. The solid built form would actually reduce: the existing pitched roof disappears and the new guarding is designed as a visually lightweight intervention. The proposal is therefore conceived not as an addition placed onto an historic building, but as an opportunity to remove awkward later fabric while adding contemporary amenity.

Photograph
Site progress or a completed area. Class hc-card-img.
2026
Responding to heritage advice rather than defending the first idea

The initial broad pre-application received objections to elements of the loft proposals, including dormers, a rooflight and a staircase. Rather than simply resubmitting the same design, we changed it. The prominent rooflight was removed entirely. The quantity of dormers was reduced and their position redesigned around newly identified existing roof geometry so that they could be more effectively concealed. The staircase was then reconsidered using new evidence demonstrating that the short section of balustrade affected is not original fabric and that much of the loft landing construction is itself modern. This iterative process is important to the case study: conservation engagement is being used to improve the scheme rather than merely secure an approval.

Photograph
The completed building. Class hc-card-img.
Ongoing
Repair first

The building contains 24 recorded windows. Our current approach is deliberately conservative: retention is the default. No sash is proposed for replacement simply because it is in poor condition. Individual windows are being investigated to establish date, timber, joinery profile, mechanism, glazing and surviving historic glass. Repair and local timber splicing are preferred wherever possible, and historic cylinder or crown glass is to remain in place or be carefully reset where intervention becomes unavoidable. The current strategy expressly avoids introducing double-glazed units where doing so would compromise historic proportions. At the same time, surviving internal shutters are being investigated for reinstatement - a conservation benefit and a practical one, since restoring their historic function helps reduce solar gain before any mechanical cooling is required.

Ongoing
Repairing without erasing evidence

Much of the internal panelling and decorative treatment appears to relate to the major 2003 office refurbishment, but we are not assuming that all of it does. The current methodology divides finishes according to evidential confidence. Modern fabric can be repaired and redecorated conventionally. Uncertain or potentially historic joinery is instead recorded and subjected to paint analysis before abrasive preparation takes place. No wholesale stripping or replacement of panelling is proposed. This is a more forensic approach than simply specifying a decorative refurbishment and is particularly appropriate to a Grade II* building.

2026–ongoing
A phased programme rather than a single refurbishment

The project is being deliberately progressed through a sequence of relatively focused consents and pre-application enquiries. Two Listed Building Consents have already been secured, while additional packages concerning the basement, rear roof, loft, internal finishes, windows, shutters and environmental systems are being developed through targeted consultation. That approach allows each part of the building to be understood properly rather than bundling a large number of interventions into a single application and treating them as though they carry equal heritage impact. The office can consequently continue functioning while its longer-term conservation programme develops.

Feature

Knowing what is old before deciding what must stay

Listed-building work can become unnecessarily restrictive when every existing element is assumed to carry equal significance. At Old Brewery House, archival research has allowed us to replace assumption with evidence. For example, the 2003 consent records widespread internal redecoration, new doors and linings, new cornices, plasterboard linings, partitioning and other internal alterations. The same historic submission demonstrates that the present rear roof and the partial blocking of a former opening are products of modern interventions rather than surviving Georgian fabric. That distinction is fundamental. It enables us to be more protective of genuinely historic fabric precisely because we are not treating later work as though it carries the same significance.

Render
Perspective. Class hc-ren.
Caption
Drawing
Elevations. Class hc-drw.
Caption - and scale
Render or drawing
Detail.
Caption
Drawing
Plans. Class hc-drw.
Caption - and scale
Drawing
Plan showing the route or the strategy. Class hc-drw.
Caption
Render
Model view. Class hc-ren.
Caption
Building services

Shrinking the machine

Comfort cooling creates a familiar problem in listed buildings: the external condenser. Rather than place conventional plant against a historic elevation or within the courtyard, the current proposal uses a fully internal VRV system. No external condensing unit is proposed. More importantly, the mechanical design is being developed only after passive measures have been considered: repair and understand the glazing, reinstate working shutters, use natural purge ventilation where possible, calculate the remaining cooling requirement, and size mechanical plant to that residual load. The project documents describe the logic succinctly: improving the passive measures shrinks the machine.

Drawing - large
Elevation or facade detail. Class hc-drw.
Caption - and scale
Drawing - large
Coordinated floor plan. Class hc-drw.
Caption - and scale
Our office

Architecture as an ongoing act of stewardship

Old Brewery House will never be a project which is simply finished. That is part of its value. As our own office, it gives the practice a direct relationship with the long-term consequences of its architectural decisions. We will work in the spaces we alter, maintain the materials we specify and experience the environmental performance of the interventions we make. The building therefore operates simultaneously as our Henley workplace, an investment in an important historic property, a live conservation project, a test bed for sensitive building-services integration, and a demonstration of the standard of repair and material quality we expect on our clients' buildings. Few practices can show their own Grade II building as the physical expression of their conservation philosophy.

Photograph - wide
The widest of the three. Class hc-shot.
Caption
Photograph
Interior or detail. Class hc-shot.
Caption
Photograph
Interior or detail. Class hc-shot.
Caption
Outcome

What the project delivered

01
Cohanim's own Henley office established within a Grade II* listed 18th-century building
02
Detailed reconstruction of the property's planning and alteration history to distinguish significant historic fabric from later intervention
03
Listed Building Consent secured for removal and replacement of modern kitchenette and WC installations
04
Façade conservation consent secured for lime repointing, masonry repair, rainwater-goods repair and controlled cleaning
05
Façade works formally recognised by the Heritage Officer as an enhancement
06
Approximately 48 sqm basement identified for improved productive use through a conservation-led headroom strategy
07
Rear roof strategy developed around removal of documented modern fabric and reinstatement of a historic opening
08
Loft proposals materially redesigned in response to Heritage Officer feedback and new physical evidence
09
All 24 windows surveyed, with repair and retention adopted as the default approach
10
Historic shutters proposed for reinstatement as both a heritage and passive environmental measure
11
Fully internal comfort-cooling strategy developed to avoid conventional external condenser plant on the listed building
12
Room-by-room conservation methodology being developed for panelling, joinery and decorative finishes
Chronology

Chronological summary

DateMatterAchievement
Pre-2026Historic researchPlanning, Listed Building and alteration history from the 1970s, 1980s, 1990s and 2003–04 assembled and reviewed
Early 2026Existing-building analysisDetailed survey undertaken of plans, fabric, windows, basement, roof and existing office accommodation
Early 2026Broad pre-applicationP26/S0789/PEM submitted covering the wider conservation and refurbishment strategy
8 May 2026Pre-app responseBroad support received for restorative/external works; specific concerns identified over parts of the roof/loft package
11 Jun 2026Cohanim officeOld Brewery House became Cohanim Architecture's new Henley office
16 Jun 2026P26/S1216/LBListed Building Consent granted for replacement of modern kitchenette and WC fixtures
Jun–Aug 2026Historic research2003–04 drawings and specifications used to distinguish modern interventions from earlier fabric
11 Aug 2026P26/S2366/LBListed Building Consent granted for façade conservation works; Heritage Officer described the works as an enhancement
12–13 Aug 2026Rear roof strategyFocused pre-application prepared for removal of modern rear roof, roof terrace and reinstatement of historic opening
Aug 2026Basement strategyPre-application developed to increase basement headroom using modern slab and ceiling fabric while retaining historic arches and piers
Aug 2026Loft strategyDormers reduced and repositioned; prominent rooflight withdrawn; staircase reconsidered using new fabric evidence
Aug 2026Internal conservationSeparate pre-application prepared for panelling, joinery and decorative repairs with paint-analysis safeguards
Aug 2026Windows / shutters24-window survey used to establish a repair-first conservation strategy and assess reinstatement of shutters
Aug 2026Environmental strategyPassive measures and fully internal VRV comfort cooling developed to minimise intervention to historic elevations
2026–ongoingPhased refurbishmentFurther Listed Building, planning and technical packages being progressed while the building remains in office use
In their words

Quotes

Quote to be supplied. Leave the slot visible until there is a real quote from a named person - do not write one on their behalf.
Project architect · Cohanim Architecture
Quote to be supplied.
Consultant - planning, heritage or engineering
Quote to be supplied.
Client
Quote to be supplied. Delete any slot that will stay empty.
Contractor or operator